Week 4 arrives and all continues to go well. All 4 courts have now had the aggregate applied and levelled.

The cabling for the floodlights has now been laid and the trenches are currently being filled. By the end of the week this work should be complete.

The surface has now been ordered along with the court wind breakers.

Courts 5 and 6 should be accessible up until Monday 20th April when the tarmacadam base will be laid at which point access will be denied for at least 2 weeks.

Keep watching this space for further updates.